aaa成人,欧美黑人xxxx猛性大交,致命弯道2在线观看免费完整版在线,亚洲情侣视频,91成人在线网站,色戒完整版免费观看无删减版,99综合网

軟題庫 移動APP 掃碼下載APP 隨時隨地移動學(xué)習(xí) 培訓(xùn)課程
試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-3
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-3》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

In an eight-month project, the customer requests a change to a complex business requirement. Development is 72% complete. The customer suggests the project schedule be extended by an additional month. What should the project manager do next?
A、Reject the change since most of the development is complete.
B、Ask for additional funds.
C、Analyze the variance.
D、Accept the change since the customer has increased the schedule.


相關(guān)試題

推薦文章
合作網(wǎng)站內(nèi)容