試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-1
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-1》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

A senior manager responsible for business transaction identified a system requirement to control the trading risks. The senior manager drafts document required to demonstrate rationality and establish boundaries for the project. A senior manager asks the project manager to starts project planning immediately. What should the project manager do first?
A、 Identify stakeholders.
B、 Develop project charter
C、 Define the project scope.
D、 Write a business case.